Bentley HAMMER CONNECT Edition Help

Tools Menu

The Tools menu contains the following commands:

Active Topology Selection Opens a Select dialog to select elements in the drawing to make them Inactive or Active.
ModelBuilder Opens the ModelBuilder Connections Manager, where you can create, edit, and manage ModelBuilder connections to be used in the model-building/model-synchronizing process.
TRex Opens the TRex wizard where you can assign elevation to model nodes using data from outside sources.
SCADAConnect Simulator Opens the SCADAConnect Simulator where you can add or edit SCADA connections.
Skelebrator Skeletonizer Opens the Skelebrator manager, where you can define and perform skeletonization operations.
LoadBuilder Opens the LoadBuilder manager where you can assign demands to model nodes using data from outside sources.
Thiessen Polygon Opens the Wizard used to create Thiessen polygons for use with LoadBuilder.
Demand Control Center Opens the Demand Control Center manager where you can add new demands, delete existing demands, or modify existing demands.
Unit Demand Control Center Opens the Unit Demand Control Center manager where you can add new unit demands, delete existing unit demands, or modify existing unit demands.
Scenario Comparison The scenario comparison tool enables you to compare input values between any two scenarios to identify differences quickly.
Hyperlinks Associate external files, such as pictures or movie files, with elements in the model.
User Data Extensions Opens the User Data Extension dialog box, which allows you to add and define custom data fields. For example, you can add new fields such as the pipe installation date.
Assign Isolation Valves to Pipes Opens the Assign Isolation Valves to Pipes where you can find and assign isolation valves to their closest pipes according to user-defined tolerances.
Batch Pipe Split Opens the Batch Pipe Split dialog.
Batch Morph Opens the Batch Morph dialog.
Wave Speed Calculator Opens the Wave Speed Calculator dialog.
Copy Initial Conditions Opens the Initial Conditions dialog.
Database Utilities Opens a menu containing the following commands: Compact Database —When you delete data from a HAMMER CONNECT project, such as elements or alternatives, the database store that HAMMER CONNECT uses can become fragmented, causing unnecessarily large data files, which impact performance substantially. Compacting the database eliminates the empty data records, thereby defragmenting the datastore and improving the performance of the file.
Note: Every tenth time a file is saved, Bentley HAMMER CONNECT will automatically prompt you to compact the database. If you open a file without saving it, the count does not go up. If you open and save a file multiple times in the same session, the count only goes up on the first save. If you open, save, and close the file, the count goes up. Click Yes to compact the database, or no to close the prompt dialog box without compacting. Since compacting the database can take time, especially for larger models, you may want to postpone the compact procedure until a later time. You can modify how HAMMER CONNECT compacts the database in the Options dialog box.
Synchronize Drawing —Synchronizes the current model drawing with the project database. Update Database Cache —Updates the current model to reflect any changes made in the database. Update Results From Project Directory—This command copies the model result files (if any) from the project directory (the directory where the project .sqlite file is saved) to the custom result file directory. The custom result directory is specified in Tools>Options>Project tab. This allows you to make a copy of the results that may exist in the model's save directory and replace the current results being worked on with them. Copy Results to Project Directory—This command copies the result files that are currently being used by the model to the project directory (where the project .sqlite is stored).
Layout Opens a menu that lists each of the available element types. Select one of the element types to place that element in your model.
External Tools Run an existing external tool or create a new one by opening up the External Tools manager.
Options Opens the Options dialog box, which allows you to change Global settings, Drawing, Units, Labeling, and ProjectWise.